Questions: Net Present Value (NPV)

5 questions to test your understanding

Score: 0 / 5
Question 1 Multiple Choice

Two mutually exclusive projects both have positive NPV at a 10% discount rate. Project A has NPV = $50,000 and IRR = 15%. Project B has NPV = $80,000 and IRR = 12%. Which should the firm choose?

AProject A — a higher IRR always indicates a more profitable investment
BProject B — NPV directly measures value created and consistently ranks mutually exclusive projects correctly
CProject A — the higher percentage return dominates in absolute value terms
DIt cannot be determined without knowing each project's payback period
Question 2 Multiple Choice

A project has NPV = 0 at the firm's discount rate. This means:

AThe project should be rejected — it generates no surplus and therefore wastes capital
BThe project exactly earns the opportunity cost of capital and is borderline acceptable — it neither creates nor destroys value above the benchmark
CThe project's total cash inflows are exactly equal to its initial cost in nominal terms
DThe discount rate used was 0%, so cash flows were not adjusted for time value
Question 3 True / False

Net present value and accounting profit measure the same underlying concept — how much an investment earns — but use different scales.

TTrue
FFalse
Question 4 True / False

A project can have a positive NPV at a low discount rate and a negative NPV at a high discount rate — the accept/reject decision can flip entirely based on the chosen discount rate.

TTrue
FFalse
Question 5 Short Answer

Why is the discount rate in an NPV calculation not just a technical parameter but a judgment about risk, and what are the consequences of choosing the wrong rate?

Think about your answer, then reveal below.